Microsoft has withdrawn from Nscale’s planned Loughton AI data centre in the UK, leaving the project without its only publicly announced customer amid reported power grid constraints.
UK neocloud provider Nscale is set to lose Microsoft as the anchor tenant at its Loughton data center in Essex, after delays in power availability disrupted plans to support AI computing services....
Microsoft ends involvement in project planned as UK's largest AI data centre, after grid connection delayed to 2030s
Would have been Nscale's anchor tenant at the site
Planned development in Loughton was set to deliver 50 MW of AI capacity and create 250 permanent jobs
The US tech giant, one of Nscale's two largest customers, recently terminated its agreement for the data center in Loughton, Essex, according to the report.
Microsoft has reportedly terminated its agreement for Nscale’s data centre in Loughton, Essex, after repeated project delays. The UK power grid is not expected to supply the site until the 2030s,...
Microsoft has pulled out of a data center deal with British cloud provider Nscale, Britain's Telegraph newspaper reported on Sunday.
US tech giant abandons agreement to lease capacity at neocloud’s UK site
Microsoft Corp. has pulled out of a UK data center deal with British neocloud Nscale at a critical time for the startup’s initial public offering hopes, the Telegraph reported.
Microsoft’s reported withdrawal from Nscale’s proposed Essex data center deal adds uncertainty to the British cloud provider’s expansion plans as it prepares for a potential US IPO.
First reported:
First saved on ClustZ:
Coverage updated:
We use cookies to improve your experience and analyze site traffic. By clicking "Accept", you agree to our use of cookies. See our Privacy Policy.